Huntly-Stratford transmission line: Mt Pirongia area
Abstract
The events of line route determination and compensation in
the contentious Mt. Pirongia region of the Huntly-Stratford 220kV
transmission line has prompted me to carry out this project in
the hope that it will contribute to and initiate action so that
this unfortunate and unnecessary episode never occurs again.
Residing within this area in question, I have witnessed the
attitudes and approaches by E.D. staff, the unity and resolve of
communities to obtain unbiased evaluations, the pressure placed
on individuals, families and districts by E.D.'s actions, the
further resolve of landowners to refuse admittance to E.D. until
they agreed to more realistic levels of compensation, and the
protracted compensation settlements. In all, a protracted, costly
and character testing episode.... [Show full abstract]
Keywords
Huntly-Stratford transmission line; Mt. Pirongia; compensation; public attitudes; transmission lines; high voltageFields of Research
1605 Policy and Administration; 050205 Environmental ManagementDate
1988Type
MonographAccess Rights
This Kellogg Rural Leaders Programme report can be viewed only by current staff and students of Lincoln University.Collections